Coming years Rijkswaterstaat will refit the Barrages of the river Nederrijn in the Netherlands. Part of the rifit is renewing of all six steel bows on Amerongen, Driel and Hagestein. A temporary steel bow (TKM) as to be placed and tested, before starting the renewing job.

Project Details:

Number: HST-16092
Client: BSB Staalbouw
Project: Installation TKM
Year: 2016
Weight: 2 x 140 t.
Site Location: Amerongen (NL)


Works Description:

Coming years Rijkswaterstaat will refit the Barrages of the river Nederrijn in the Netherlands. Part of the rifit is renewing of all six steel bows on Amerongen, Driel and Hagestein. A temporary steel bow (TKM) as to be placed and tested, before starting the renewing job. Hebo assisted by the transport and installations works on site. After placing and connecting the two steel elements we installed concrete closure plates. Also the fulcrums in the basement where set dry and inspected. After a successful test we transported the TKM to a storage place, ready for next year.

Equipment on site:

  • Sheerleg HEBO-Lift 6
  • Pusher Tug Catharina 5
  • Several barges
  • HEBO-Cat 7
  • HEBO-Cat 15
  • Cranebarge P6 + LTR1100
  • Diving Team