Trambrug Zwijnaarde

portfolio-projecten-trambrug-zwijnaarde-klein.jpg

We received the assignment for the transportation and installation of the Bridge from VBSC. The assignment entailed transporting the bridge in 3 parts from the VBSC quay in Bumar Gent to the working s ite on the canal at Zwijnaarde and placing it them the correct position in between the supporting pylons.

Project Details:

Number: HST-15079
Client: Victor Buyck Steel Constructions NV
Project: Trambrug Zwijnaarde
Year: 2015
Weight: 585t
Site Location: Zwijnaarde (B)


Works Description:

We received the assignment for the transportation and installation of the Bridge from VBSC. The assignment entailed transporting the bridge in 3 parts from the VBSC quay in Bumar Gent to the working s ite on the canal at Zwijnaarde and placing it them the correct position in between the supporting pylons. The bridge parts where transported by SPMT from the factory to the quay. We loaded the bridge parts from quay into inland ships by floating sheerlegs and mobile cranes. After transport we unloaded the bridge parts and placed them on the existing piles. The two site parts where placed in combination with sheerle g(s) and SPMT. The middle part over water was placed by the two sheerlegs. The challenges of this project were the narrow working area and the combination of lifting with sheerleg(s) and driving with SPMT.

Equipment on site:

  • Sheerleg HEBO-Lift 7
  • Sheerleg HEBO-Lift 8
  • 2 inland ships
  • 2 x 6 line SPMT
  • 2 x pusher tugs
  • Mobile crane(s) for assisting works
  • Several auxiliary equipment
  • Professional crew

Photos:

    

Download PDF ››