We received the assignment for the transportation of the two Bridges from Victor Buyck Steel Constructions. The assignment entailed transpor ting the bridge from the quay in Gent to the pre assembly site in Zeebrugge.

Project Details:

Number: HST-15272
Client: Victor Buyck Steel Constructions
Project: New bridges A11 Zeebrugge
Year: 2016
Weight: 1100t
Site Location: Zeebrugge


Works Description:

We received the assignment for the transportation of the two Bridges from Victor Buyck Steel Constructions. The assignment entailed transpor ting the bridge from the quay in Gent to the pre assembly site in Zeebrugge. After the assembling of the complete bridge we have installed them on the final position with a sheerlegs. Our responsibility consisted of transporting and the installation of the bridges on site. We executed the transportation with own push boats and tugs and with 40 axles lines SPMTs. Because we had to pass lower existing bridges on the canal, we had to jack down the bridge with 4x 600t jacks. Upon arrival on site we discharged the bridges on shore by means of Ro -Ro and placed them on temporary abutments from the client. Phase two consist of shore transport to quayside with SPMT’s and lift with the MATADOR III.

Equipment on site:

  • 1x 28t tugs
  • 1x CATHARINA 11; 15t tugs
  • 1x CATHARINA 8; 900hp pushboat
  • 1x barges 75,00 x 22,00mtr
  • Several winches in the capacity between 7t and 100t
  • 40 axles lines SPMT’s with two PPU
  • 4pc 600t jacking systems
  • Several auxiliary equipment
  • Professional crew